Project description:
A steel interconnection bridge was built with a span of 32,5 metres along the ICE-quick-connexion route between Oldenburg and Bremen
Due to having the shortest possible track cut-off time, the bridge was built right next to its final position. When finished it was then shifted crossways into position. The supporting arches of the steel construction were prefabricated in the factory.
Constructor:
Stahlbau Magdeburg GmbH
Planned activity: Implementation planning of the steel construction
Contract price: 1,2 m. euro
Project period: 2005 - 2006
Utilisation: Railway bridge