Construction of the new railway bridge Stephanietor

in km 42,574" line Oldenburg - Bremen

Services rendered by WoRart:

• Implementation planning for the steel construction
• Constructed volumn of steel approx.130 tonnes

 
     

Project description:

A steel interconnection bridge was built with a span of 32,5 metres along the ICE-quick-connexion route between Oldenburg and Bremen

Due to having the shortest possible track cut-off time, the bridge was built right next to its final position. When finished it was then shifted crossways into position. The supporting arches of the steel construction were prefabricated in the factory.





Constructor:

Stahlbau Magdeburg GmbH

Planned activity: Implementation planning of the steel construction

Contract price: 1,2 m. euro

Project period: 2005 - 2006

Utilisation: Railway bridge